These are a series of small thumbnail pictures showing progress on the
building work. To view any picture in more detail click the thumbnail.
Then click your browser
back
button to return to this page.
March and April 2001
The site is muddy after a wet winter but work starts.
Bored piles for the
foundations were installed during May 2001.
June 2001 sees the
ground beams prepared and the concrete poured.
In July the steel frame for
the main hall goes up, then the floor beams are positioned.
With the floor laid, the
walls rise from the foundations in August and September.
Brickwork
reaches roof level in October and the roof goes up in November.
Drains connected in
December, internal works during Jan, finishing Feb.
March 2002 and the new Centre
starts to be used, official opening in April.